Ang Imhr.ca ang pinakamahusay na lugar upang makakuha ng mabilis at tumpak na mga sagot sa lahat ng iyong mga tanong. Kumuha ng agarang at mapagkakatiwalaang sagot sa iyong mga tanong mula sa isang komunidad ng mga bihasang eksperto sa aming platform. Kumuha ng detalyado at eksaktong sagot sa iyong mga tanong mula sa isang komunidad ng mga eksperto sa aming komprehensibong Q&A platform.

2. A certain project can be completed by 10 workers in 45 days. In order to complete the project
sooner, the company plans to hire additional workers. How many workers are needed to complete the
project in 25 days?
Solution​


Sagot :

Answer:

The project needs 18 workers to be done in 25 days.

Step-by-step explanation:

the project is 10 workers × 45 days = 450 "work" divided by the workers in days

this "450 work" needs to be done in 25 days so there's a need for 450/25 = 18 workers to do the work

thus, they need to add 8 more workers

10 workers × 45 days = x workers × 25 days

10 workers × 45 days ÷ 25 days = x workers

x workers = 18 workers

Pinahahalagahan namin ang iyong oras sa aming site. Huwag mag-atubiling bumalik kailanman mayroon kang mga karagdagang tanong o kailangan ng karagdagang paglilinaw. Pinahahalagahan namin ang iyong oras. Mangyaring bumalik anumang oras para sa pinakabagong impormasyon at mga sagot sa iyong mga tanong. Maraming salamat sa pagbisita sa Imhr.ca. Bumalik muli para sa higit pang kapaki-pakinabang na impormasyon at sagot mula sa aming mga eksperto.