Makakuha ng mga solusyon sa iyong mga katanungan sa Imhr.ca, ang mabilis at tumpak na Q&A platform. Itanong ang iyong mga katanungan at makakuha ng eksaktong sagot mula sa mga propesyonal na may malawak na karanasan sa iba't ibang larangan. Kumuha ng detalyado at eksaktong sagot sa iyong mga tanong mula sa dedikadong komunidad ng mga eksperto sa aming Q&A platform.

How to process the inverse variation in the number of days needed in repairing a house varies inversely a sthe number of men

Sagot :

Answer with step-by-step explanation:

Let:

y = number of days

x = number of men

k = constant of variation

The equation for inverse variation:

y = kx

and

k= xy

It means that as one variable increases, the other variable decreases.

In work rate, as more men work on a given job, the faster or fewer days it is completed. As fewer men work on the same job, the longer or more days it is completed.

Example:

  • 10 men can repair a house in 6 days. How many men are needed to complete the house in 3 days?

  • Find x, the number of men needed to complete the repairs in 3 days

Since k is constant, and k =xy, then:

xy = xy

(10)(6) = x(3)

60 = 3x

3x/3 = 60/3

x = 20

20 men are needed to complete the repairs work faster in 3 days.

Salamat sa paggamit ng aming serbisyo. Layunin naming magbigay ng pinaka-tumpak na mga sagot para sa lahat ng iyong mga katanungan. Bisitahin muli kami para sa higit pang mga kaalaman. Umaasa kaming naging kapaki-pakinabang ang aming mga sagot. Bumalik anumang oras para sa higit pang tumpak na mga sagot at napapanahong impormasyon. Imhr.ca ay laging nandito para magbigay ng tamang sagot. Bisitahin muli kami para sa pinakabagong impormasyon.