Makakuha ng mga solusyon sa iyong mga katanungan sa Imhr.ca, ang mabilis at tumpak na Q&A platform. Kumuha ng mga sagot mula sa mga eksperto nang mabilis at eksakto mula sa aming dedikadong komunidad ng mga propesyonal. Maranasan ang kaginhawaan ng paghahanap ng eksaktong sagot sa iyong mga tanong mula sa mga bihasang propesyonal sa aming platform.

1.
Computation. Compute the number of CHB and Reinforced bar needed on the given
scenario. (Each RSB is 6 meters in length and the height of CHB id 18 cm.)
1. A wall 1.1 meters from the ground with a length of 3 meters is to be constructed using a 4"
concrete hollow block (CHB). 2 layers of CHB will be buried on the ground. The distance of the
vertical reinforce steel bar (RSB) is 60cm and the horizontal RSB is to be placed after every 3
layers of CHB.

Sagot :

Answer:

To compute the number of CHB (Concrete Hollow Blocks) and Reinforced Steel Bars (RSB) needed for the given scenario, we will follow these steps:

Given:

- Wall height: 1.1 meters from the ground

- Wall length: 3 meters

- CHB height: 4 inches (equivalent to 10.16 cm)

- 2 layers of CHB will be buried on the ground

- Vertical RSB spacing: 60 cm

- Horizontal RSB to be placed after every 3 layers of CHB

- Each RSB is 6 meters in length

Let's calculate the number of CHB needed first:

1. Calculate the total height of the wall including the buried CHB:

Total wall height = Wall height + 2 * CHB height

Total wall height = 1.1 meters + 2 * 10.16 cm = 1.1 meters + 20.32 cm = 1.1 meters + 0.2032 meters = 1.3032 meters

2. Calculate the number of CHB layers:

Number of CHB layers = Total wall height / CHB height

Number of CHB layers = 1.3032 meters / 0.18 meters = 7.239 (round up to 8 layers for safety)

3. Calculate the total number of CHB needed:

Total CHB needed = Wall length * Number of CHB layers

Total CHB needed = 3 meters * 8 layers = 24 CHB

Next, let's calculate the number of RSB needed:

4. Calculate the number of horizontal RSB needed:

Number of horizontal RSB = Number of CHB layers / 3 (placed after every 3 layers)

Number of horizontal RSB = 8 layers / 3 ≈ 2.67 (round up to 3 bars for safety)

5. Calculate the number of vertical RSB needed:

Number of vertical RSB = Wall length / Vertical RSB spacing

Number of vertical RSB = 3 meters / 0.6 meters = 5 bars

Therefore, for the given scenario, you would need:

- 24 Concrete Hollow Blocks (CHB)

- 3 Horizontal Reinforced Steel Bars (RSB)

- 5 Vertical Reinforced Steel Bars (RSB)

Explanation:

Sana makatulong. Pa follow then pa brainliest answer po! Tysm, God bless ❤️

# Carry on learning ✨

Salamat sa paggamit ng aming plataporma. Lagi kaming narito upang magbigay ng tumpak at napapanahong mga sagot sa lahat ng iyong mga katanungan. Umaasa kami na nakatulong ito. Mangyaring bumalik kapag kailangan mo ng higit pang impormasyon o mga sagot sa iyong mga katanungan. Maraming salamat sa pagtiwala sa Imhr.ca. Bisitahin kami ulit para sa mga bagong sagot mula sa mga eksperto.